Process:

Zhaoyang: Add the Time bar feature in the APP and complete the Speech API.

Yandong: Do some code review in the Backend server.

Fuchen: Do some code review in the IOS app.

Minlong: Complete the final resful debug and do some code integration.

Dong: Check the Code about the Azure Server.

 

Plan:

The user study in the ALPHA release is in progress. And the final results will guide us to change some UI design for BETA release and optimal the code performance.